PMI Agile Certified Practitioner (PMI-ACP) is a certification offered by the Project Management Institute (PMI) for professionals who work in agile methodologies or want to become proficient in this approach. The PMI-ACP exam is designed to test a professional's knowledge and skills in agile principles, practices, tools, and techniques. PMI Agile Certified Practitioner certification provides a competitive advantage to professionals seeking to demonstrate their expertise in agile methodologies.
NEW QUESTION # 62
During the iteration planning of a newly onboarded agile team, the product owner adds a set of high priority user stories into the iteration backlog.
What should the team do first to define the tasks needed to implement the user stories?
- A. Assign tasks to each team member
- B. Self-organize
- C. Meet with the customer
- D. Identify the Scrum Master
Answer: D
Explanation:
Explanation/Reference: https://www.scaledagileframework.com/iteration-planning/
NEW QUESTION # 63
Collaboration can be defined as working together to jointly produce a deliverable or make a decision, whereas coordination is:
- A. Agreeing on a due date.
- B. Sharing information.
- C. Agreeing on the design.
- D. Pair programming.
Answer: B
Explanation:
Explanation/Reference:
NEW QUESTION # 64
Which of the following is not part of Agile Discovery?
- A. Describe essential governance and organization aspects of the project and how the project will be managed
- B. Document business outcomes that are quantifiable and measureable
- C. Define the tasks that the team will perform during an iteration
- D. Outline a plan for the technical and business architecture/design of the solution
Answer: C
NEW QUESTION # 65
Continuous attention to_____________ and good design enhances agility.
- A. Best architectures
- B. Robust plans
- C. Change control
- D. Technical excellence
Answer: D
NEW QUESTION # 66
During a daily stand up meeting, a developer expresses concerns that the selected technology limits the number of concurrent users. What should the agile team lead do?
- A. Ask the team to conduct research to find a viable solution.
- B. Select a better technology for team implementation.
- C. Consult the product owner about their non-functional requirements.
- D. Obtain customer input on their technology requirements.
Answer: D
NEW QUESTION # 67
When does a Sprint get canceled or end early?
- A. When the Sprint backlog is complete
- B. When the definition of "Done" is met
- C. When a key resource is out sick
- D. When the Sprint Goal cannot be met
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION # 68
The ScrumMaster notices repeated friction between two team members in the Daily Scrum meetings. The next step should be to:
- A. Ask for new resources to replace them before the friction undermines the team's productivity.
- B. Attempt to resolve the problem directly and immediately during a Daily Scrum meeting.
- C. Ignore the friction because a self-organizing team must sort out team conflict issues.
- D. Schedule a meeting with them after a Daily Scrum meeting to explore and resolve the issue.
Answer: D
NEW QUESTION # 69
In Scrum, the development team decides which events or ceremonies take place during a Sprint.
- A. False
- B. True
Answer: A
Explanation:
Explanation
NEW QUESTION # 70
A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?
- A. Process flows and personas
- B. Personas and extreme characters
- C. Information radiators and story maps
- D. Information radiators and wireframes
Answer: C
NEW QUESTION # 71
The key elements of a user story in Agile development are:
- A. conversations about the story, a written description, and success criteria about the story.
- B. the story points estimate, conversations about the story, and an agreed priority.
- C. tests to determine when the story is done, a written description, and the planned release.
- D. a written description, the story points estimate, and the planned release.
Answer: A
Explanation:
Explanation/Reference:
NEW QUESTION # 72
What is used to provide a simple medium for gathering basic information about stories, recording high-level requirements, developing work estimates, and defining acceptance tests?
- A. Storyboard
- B. Burndown chart
- C. Story card
- D. Retrospective
Answer: C
NEW QUESTION # 73
The purpose of the iteration retrospective is to:
- A. Provide a demonstration of the features developed during the iteration, get feedback from users, and begin testing.
- B. Report progress of the work effort, what work will be done next, and review impediments to progress.
- C. Prioritize the Product Backlog, generate development and testing estimates, and plan the next iteration.
- D. Identify what worked well, what did not work well, and what actions should be taken to improve the process.
Answer: D
NEW QUESTION # 74
An archetypal user of a systems is called a(n):
- A. Super user
- B. Admin
- C. UX engineer
- D. Persona
Answer: D
NEW QUESTION # 75
After three iterations, it is identified that a project's underlying security structure architecture is unstable.
While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?
- A. Meet with the team and stakeholders to address rework and rewrite stories as needed.
- B. Cancel the current sprint, and meet with stakeholders to reassess the project's validity.
- C. Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.
- D. Ask the development team to address the issue since it is in their domain.
Answer: D
NEW QUESTION # 76
Which layer of the product planning structure defines details at the capability or feature level?
- A. Iteration
- B. Wave
- C. Release
- D. Roadmap
Answer: C
NEW QUESTION # 77
An agile team has only one database administrator with the necessary knowledge of database- related tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
- A. Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.
- B. Move this database administrator to another team so that team members learn database-related tasks.
- C. Add another database administrator to balance the workload and aid with knowledge retention.
- D. Start the hiring process for a new, equally skilled database administrator as a replacement.
Answer: D
NEW QUESTION # 78
Test-Driven Development (TDD) is a rapid cycle of:
- A. Testing, refactoring, and validation.
- B. Requirements, coding, and refactoring.
- C. Requirements, coding, and testing.
- D. Testing, coding, and refactoring.
Answer: D
NEW QUESTION # 79
When managing an agile software team, engaging the business in prioritizing the backlog is an example of:
- A. Vendor management
- B. Technical risk reduction
- C. Stakeholder story mapping
- D. Incorporating stakeholder values
Answer: D
NEW QUESTION # 80
Collaboration can be defined as working together to jointly produce a deliverable or make a decision, whereas coordination is:
- A. Agreeing on a due date.
- B. Sharing information.
- C. Agreeing on the design.
- D. Pair programming.
Answer: B
NEW QUESTION # 81
An Agile team best ensures product quality through:
- A. Quality assurance's daily collaboration with the development team.
- B. Feedback gathered during iteration retrospectives.
- C. More frequent inspection after each iteration.
- D. The development team's use of pair programming.
Answer: C
Explanation:
Explanation/Reference:
Explanation:
NEW QUESTION # 82
When is the best time to perform Earned Value Measurement (EVM) in Agile projects?
- A. During an iteration
- B. Never - we don't perform EVM in Agile
- C. After the iteration
- D. After a release
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION # 83
......
PMI-ACP Exam Overview
The PMI-ACP certification test contains 120 questions, which must be completed within 180 minutes. However, out of these 120 items, 20 are pretest questions that will not affect your overall score. They are only included in the exam as a validity testing tool for the actual questions. The certification exam is available in 6 languages, including English, Japanese, Arabic, Portuguese, Korean, and Spanish. It is delivered through the approved Pearson VUE testing centers worldwide. You can check the location of the nearest available center on the Pearson VUE website. You can also sit for your PMI-ACP exam online from the comfort of your home or office supervised by a proctor through Pearson VUE. The test costs $435 for the PMI members and $495 for the non-members.