NEW QUESTION # 16
Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?
- A. Tests should be written in executable format before the code is written and should act as executable specifications that drive coding
- B. Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly
- C. Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle
- D. Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level
Answer: C
Explanation:
The statement that refers to good testing practice to be applied regardless of the chosen software development model is option D, which says that involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle. Work product reviews are static testing techniques, in which the work products of the software development process, such as the requirements, the design, the code, the test cases, etc., are examined by one or more reviewers, with or without the author, to identify defects, violations, or improvements. Involvement of testers in work product reviews can provide various benefits for the testing process, such as improving the test quality, the test efficiency, and the test communication. The early testing principle states that testing activities should start as early as possible in the software development lifecycle, and should be performed iteratively and continuously throughout the lifecycle. Applying the early testing principle can help to prevent, detect, and remove defects at an early stage, when they are easier, cheaper, and faster to fix, as well as to reduce the risk, the cost, and the time of the testing process. The other options are not good testing practices to be applied regardless of the chosen software development model, but rather specific testing practices that may or may not be applicable or beneficial for testing, depending on the context and the objectives of the testing activities, such as:
Tests should be written in executable format before the code is written and should act as executable specifications that drive coding: This is a specific testing practice that is associated with test-driven development, which is an approach to software development and testing, in which the developers write automated unit tests before writing the source code, and then refactor the code until the tests pass. Test-driven development can help to improve the quality, the design, and the maintainability of the code, as well as to provide fast feedback and guidance for the developers. However, test-driven development is not a good testing practice to be applied regardless of the chosen software development model, as it may not be feasible, suitable, or effective for testing in some contexts or situations, such as when the requirements are unclear, unstable, or complex, when the test automation tools or skills are not available or adequate, when the testing objectives or levels are not aligned with the unit testing, etc.
Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level: This is a specific testing practice that is associated with sequential software development models, such as the waterfall model, the V-model, or the W-model, in which the software development and testing activities are performed in a linear and sequential order, with well-defined phases, deliverables, and dependencies. Test levels are the stages of testing that correspond to the levels of integration of the software system, such as component testing, integration testing, system testing, and acceptance testing. Test levels should have clear and measurable entry criteria and exit criteria, which are the conditions that must be met before starting or finishing a test level. In sequential software development models, the exit criteria of one test level are usually part of the entry criteria for the next test level, to ensure that the software system is ready and stable for the next level of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be relevant, flexible, or efficient for testing in some contexts or situations, such as when the software development and testing activities are performed in an iterative and incremental order, with frequent changes, feedback, and adaptations, as in agile software development models, such as Scrum, Kanban, or XP, when the test levels are not clearly defined or distinguished, or when the test levels are performed in parallel or concurrently, etc.
Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly: This is a specific testing practice that is associated with uniform software development models, such as the spiral model, the incremental model, or the prototyping model, in which the software development and testing activities are performed in a cyclical and repetitive manner, with similar phases, deliverables, and processes. Test objectives are the goals or the purposes of testing, which can vary depending on the test level, the test type, the test technique, the test environment, the test stakeholder, etc. Test objectives can be defined in terms of the test basis, the test coverage, the test quality, the test risk, the test cost, the test time, etc. Test objectives should be specific, measurable, achievable, relevant, and time-bound, and they should be aligned with the project objectives and the quality characteristics. In uniform software development models, the test objectives may be the same for all test levels, as the testing process is repeated for each cycle or iteration, with similar focus, scope, and perspective of testing. However, this is not a good testing practice to be applied regardless of the chosen software development model, as it may not be appropriate, realistic, or effective for testing in some contexts or situations, such as when the software development and testing activities are performed in a hierarchical and modular manner, with different phases, deliverables, and dependencies, as in sequential software development models, such as the waterfall model, the V-model, or the W-model, when the test objectives vary according to the test levels, such as component testing, integration testing, system testing, and acceptance testing, or when the test objectives change according to the feedback, the learning, or the adaptation of the testing process, as in agile software development models, such as Scrum, Kanban, or XP, etc. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.1.1, Testing and the Software Development Lifecycle1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.1, Testing Principles1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.2, Testing Policies, Strategies, and Test Approaches1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 1.3.1, Testing in Software Development Lifecycles1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.2, Test Monitoring and Control1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.3, Test Analysis and Design1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.4, Test Implementation1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.5, Test Execution1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.6, Test Closure1 ISTQB® Glossary of Testing Terms v4.0, Work Product Review, Static Testing, Early Testing, Test-driven Development, Test Level, Entry Criterion, Exit Criterion, Test Objective, Test Basis, Test Coverage, Test Quality, Test Risk, Test Cost, Test Time2
NEW QUESTION # 17
For each of the test cases to be executed, the following table specifies the priority order and dependencies on other test cases
Which of the following test execution schedules is compatible with the logical dependencies and allows executing the test cases in priority order?
- A. TC4, TC6, TC3, TC2, TC5, TC1
- B. TC4, TC3, TC2, TC6, TC5. TC1
- C. TC3, TC5, TC6, TC1, TC4, TC3
- D. TC4, TC3,TC2,TC6,TC1,TC5
Answer: D
Explanation:
Explanation
This answer is correct because it follows the logical dependencies and allows executing the test cases in priority order. TC4, TC3, and TC2 are executed first because they have the highest priority. TC6 is executed next because it has a logical dependency on TC2. TC1 is executed next because it has a logical dependency on TC5. Finally, TC5 is executed last because it has the lowest priority. References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 documents
NEW QUESTION # 18
Which of the following is not an example of a typical content of a test completion report for a test project?
- A. The unexpected test environment downtime that resulted in slower test execution
- B. The additional effort spent on test execution compared to what was planned
- C. The residual risk level if a risk-based test approach was adopted
- D. The test procedures of all test cases that have been executed
Answer: D
Explanation:
Explanation
This answer is correct because the test procedures of all test cases that have been executed are not a typical content of a test completion report for a test project. A test completion report is a document that summarizes the test activities and results at the end of a test project. It usually includes information such as the test objectives, scope, approach, resources, schedule, results, deviations, issues, risks, lessons learned, and recommendations for improvement. The test procedures of all test cases that have been executed are part of the test documentation, but they are not relevant for the test completion report, as they do not provide a high-level overview of the test project outcomes and performance. References: ISTQB Foundation Level Syllabus v4.0, Section 2.5.3.2
NEW QUESTION # 19
Which of the following statements is true?
- A. Some of the most common test basis used by white-box test techniques include user stories, use cases and business processes
- B. Experience-based test techniques are often useful to detect hidden defects that have not been targeted by black-box test techniques
- C. The primary goal of experience-based test techniques is to design test cases that can be easily automated using a GUI-based test automation tool
- D. Experience-based test techniques rely on the experience of testers to identify the root causes of defects found by black-box test techniques
Answer: B
Explanation:
Experience-based test techniques are test design techniques that rely on the experience, knowledge, intuition, and creativity of the testers to identify and execute test cases that are likely to find defects in the software system. Experience-based test techniques are often useful to detect hidden defects that have not been targeted by black-box test techniques, which are test design techniques that use the external behavior and specifications of the software system as the test basis, without considering its internal structure or implementation. Experience-based test techniques can complement black-box test techniques by covering aspects that are not explicitly specified, such as usability, security, reliability, performance, etc. The other statements are false, because:
Experience-based test techniques do not rely on the experience of testers to identify the root causes of defects found by black-box test techniques, but rather to identify the potential sources of defects based on their own insights, heuristics, or exploratory testing. The root causes of defects are usually identified by debugging or root cause analysis, which are activities that involve examining the code or the development process to find and fix the errors that led to the defects.
Some of the most common test basis used by white-box test techniques include the source code, the design documents, the architecture diagrams, and the control flow graphs of the software system. White-box test techniques are test design techniques that use the internal structure and implementation of the software system as the test basis, and aim to achieve a certain level of test coverage based on the code elements, such as statements, branches, paths, etc. User stories, use cases, and business processes are examples of test basis used by black-box test techniques, as they describe the functional and non-functional requirements of the software system from the perspective of the users or the stakeholders.
The primary goal of experience-based test techniques is not to design test cases that can be easily automated using a GUI-based test automation tool, but rather to design test cases that can reveal defects that are not easily detected by other test techniques, such as boundary value analysis, equivalence partitioning, state transition testing, etc. Test automation is the use of software tools to execute test cases and compare actual results with expected results, without human intervention. Test automation can be applied to different types of test techniques, depending on the test objectives, the test levels, the test tools, and the test resources. However, test automation is not always feasible or beneficial, especially for test cases that require human judgment, creativity, or exploration, such as those designed by experience-based test techniques. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.1, Black-box Test Design Techniques ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.2, White-box Test Design Techniques ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 2.2.3, Experience-based Test Design Techniques ISTQB® Glossary of Testing Terms v4.0, Experience-based Test Technique, Black-box Test Technique, White-box Test Technique, Test Basis, Test Coverage, Test Automation
NEW QUESTION # 20
Which of the following issues cannot be identified by static analysis tools?
- A. Very low MTBF (Mean Time Between failure)
- B. Security vulnerabilities
- C. Potentially endless loops
- D. Referencing a variable with an undefined value
Answer: A
Explanation:
Static analysis tools are software tools that examine the source code of a program without executing it. They can detect various types of issues, such as syntax errors, coding standards violations, security vulnerabilities, and potential bugs12. However, static analysis tools cannot identify issues that depend on the runtime behavior or performance of the program, such as very low MTBF (Mean Time Between failure)3. MTBF is a measure of the reliability of a system or component. It is calculated by dividing the total operating time by the number of failures. MTBF reflects how often a system or component fails during its expected lifetime. Static analysis tools cannot measure MTBF because they do not run the program or observe its failures. MTBF can only be estimated by dynamic testing, which involves executing the program under various conditions and collecting data on its failures4. Therefore, very low MTBF is an issue that cannot be identified by static analysis tools. The other options, such as potentially endless loops, referencing a variable with an undefined value, and security vulnerabilities, are issues that can be identified by static analysis tools. Static analysis tools can detect potentially endless loops by analyzing the control flow and data flow of the program and checking for conditions that may never become false5. Static analysis tools can detect referencing a variable with an undefined value by checking the scope and initialization of variables and reporting any use of uninitialized variables6. Static analysis tools can detect security vulnerabilities by checking for common patterns of insecure code, such as buffer overflows, SQL injections, cross-site scripting, and weak encryption. Reference = What Is Static Analysis? Static Code Analysis Tools - Perforce Software, How Static Code Analysis Works | Perforce, Static Code Analysis: Techniques, Top 5 Benefits & 3 Challenges, What is MTBF? Mean Time Between Failures Explained | Perforce, Static analysis tools - Software Testing MCQs - CareerRide, ISTQB_Chapter3 | Quizizz, [Static Code Analysis for Security Vulnerabilities | Perforce].
NEW QUESTION # 21
You are testing a room upgrade system for a hotel. The system accepts three differed types of room (increasing order of luxury): Platinum. Silver and Gold Luxury. ONLY a Preferred Guest Card holder s eligible for an upgrade.
Below you can find the decision table defining the upgrade eligibility:
What is the expected result for each of the following test cases?
Customer A: Preference Guest Card holder, holding a Silver room
Customer B: Non Preferred Guest Card holder, holding a Platinum room
- A. Customer A: doesn't offer any upgrade; Customer B: doesn't offer any upgrade.
- B. Customer A: offers upgrade to Gold Luxury room; Customer B: doesn't offer any upgrade
- C. Customer A; doesn't offer any upgrade; Customer B: offers upgrade to Gold luxury room
- D. Customer A: offers upgrade to Silver room; Customer B: offers upgrade to Silver room.
Answer: B
Explanation:
According to the decision table in the image, a Preferred Guest Card holder with a Silver room is eligible for an upgrade to Gold Luxury (YES), while a non-Preferred Guest Card holder, regardless of room type, is not eligible for any upgrade (NO). Therefore, Customer A (a Preferred Guest Card holder with a Silver room) would be offered an upgrade to Gold Luxury, and Customer B (a non-Preferred Guest Card holder with a Platinum room) would not be offered any upgrade. Reference = The answer is derived directly from the decision table provided in the image; specific ISTQB Certified Tester Foundation Level (CTFL) v4.0 documents are not referenced.
NEW QUESTION # 22
Test automation allows you to:
- A. produce tests that are less subject to human errors
- B. avoid performing exploratory testing
- C. increase test process efficiency by facilitating management of defects
- D. demonstrate the absence of defects
Answer: A
Explanation:
Test automation allows you to produce tests that are less subject to human errors, as they can execute predefined test scripts or test cases with consistent inputs, outputs, and expected results. Test automation can also reduce the manual effort and time required to execute repetitive or tedious tests, such as regression tests, performance tests, or data-driven tests. Test automation does not demonstrate the absence of defects, as it can only verify the expected behavior of the system under test, not the unexpected or unknown behavior. Test automation does not avoid performing exploratory testing, as exploratory testing is a valuable technique to discover new information, risks, or defects that are not covered by automated tests. Test automation does not increase test process efficiency by facilitating management of defects, as defect management is a separate activity that involves reporting, tracking, analyzing, and resolving defects, which may or may not be related to automated tests. Reference: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB® Certified Tester Foundation Level Syllabus v4.0, Chapter 3.3.1, Test Automation1 ISTQB® Glossary of Testing Terms v4.0, Test Automation2
NEW QUESTION # 23
Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?
- A. Test-Driven Development (TDD)
- B. Domain-Driven Design (DDD)
- C. Acceptance Test-Driven Development (ATDD)
- D. Behavior-Driven Development (BDD)
Answer: D
Explanation:
Explanation
This answer is correct because Behavior-Driven Development (BDD) is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development. BDD is a collaborative approach that involves testers, developers, business analysts, product owners, and other stakeholders in defining the expected behavior of the application using scenarios that describe the preconditions, actions, and outcomes of the application. BDD scenarios are written using a domain-specific language (DSL) that can be translated into executable test cases using tools such as Cucumber or SpecFlow. BDD aims to improve communication, collaboration, and feedback among the team members, and to deliver software that meets the customer's needsand expectations. References: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.4
NEW QUESTION # 24
Mark the correct sentences:
* Defects are a result of environmental conditions and are also referred to as "Failures"
* A human mistake may produce a defect
* A system mil totally fail to operate correctly when a failure exists in it
* When a defect exists in a system it may result in a failure
* Defects occur only as a result of technology changes
- A. IV, V
- B. II, III, IV
- C. II, IV
- D. I, II
Answer: C
Explanation:
The question is about marking the correct sentences among the given statements related to defects, failures, and mistakes. According to the ISTQB glossary, the definitions of these terms are1:
Defect: A flaw in a component or system that can cause the component or system to fail to perform its required function, e.g. an incorrect statement or data definition. A defect, if encountered during execution, may cause a failure of the component or system.
Failure: An event in which a component or system does not perform a required function within specified limits.
Mistake: A human action that produces an incorrect result.
Therefore, out of the five given statements, only two are correct, namely:
A human mistake may produce a defect: This is true, as a mistake is a source or cause of a defect, e.g. a programmer may make a mistake in writing a code statement, which results in a defect in the software component.
When a defect exists in a system it may result in a failure: This is true, as a defect is a potential or actual cause of a failure, e.g. a defect in the software component may cause the system to fail to perform a required function when the defect is encountered during execution.
The other three statements are incorrect, namely:
Defects are a result of environmental conditions and are also referred to as "Failures": This is false, as defects are not a result of environmental conditions, but of mistakes or other factors, and defects are not the same as failures, but rather the causes of failures.
A system will totally fail to operate correctly when a failure exists in it: This is false, as a system may not necessarily fail completely or stop operating when a failure occurs, but may continue to operate with reduced functionality or performance, or with incorrect results.
Defects occur only as a result of technology changes: This is false, as defects can occur due to various reasons, not only technology changes, such as human mistakes, design flaws, requirement changes, hardware failures, etc.
Reference:
1: ISTQB Glossary of Testing Terms 4.0, 2023, available at ISTQB) and ASTQB).
NEW QUESTION # 25
Which of the following statements about static testing and dynamic testing is true?
- A. Unlike dynamic testing, which focuses on detecting potential defects, static testing focuses on detecting failures which may be due to actual defects
- B. Unlike dynamic testing, which can be also performed manually, static testing cannot be performed without specialized tools
- C. Both static testing and dynamic testing can be used to highlight issues associated with non-functional characteristics
- D. Static testing is usually much less cost-effective than dynamic testing
Answer: C
Explanation:
This answer is correct because static testing and dynamic testing are both types of testing that can be used to highlight issues associated with non-functional characteristics, such as usability, performance, security, reliability, etc. Static testing is a type of testing that involves the analysis of software work products, such as requirements, design, code, or test cases, without executing them. Dynamic testing is a type of testing that involves the execution of software work products, such as code or test cases, using inputs and verifying outputs. Both static testing and dynamic testing can be applied to different test levels and test types, and can use different test techniques and tools, to evaluate the non-functional characteristics of the software product. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.2.1.1, Section 2.2.1.2
NEW QUESTION # 26
Consider a given test plan which, among others, contains the following three sections: "Test Scope", "Testing Communication", and "Stakeholders". The features of the test object to be tested and those excluded from the testing represent information that is:
- A. usually included in a test plan and, in the given test plan, it is more likely to be specified within
"Stakeholders" rather than in the other two sections mentioned - B. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned
- C. not usually included in a test plan, and therefore in the given test plan it should not be specified neither within the three sections mentioned, nor within the others
- D. usually included in a test plan and, in the given test plan, it is more likely to be specified within "Testing Communication" rather than in the other two sections mentioned
Answer: B
Explanation:
Explanation
The features of the test object to be tested and those excluded from the testing represent information that is usually included in a test plan and, in the given test plan, it is more likely to be specified within "Test Scope" rather than in the other two sections mentioned. The test scope defines the boundaries and limitations of the testing activities, such as the test items, the features to be tested, the features not to be tested, the test objectives, the test environment, the test resources, the test assumptions, the test risks, etc. The test scope helps to establish a common understanding of what is included and excluded from the testing, and to avoid ambiguity, confusion, or misunderstanding among the stakeholders. The other two sections, "Testing Communication" and "Stakeholders", are also important parts of a test plan, but they do not directly address the features of the test object. The testing communication describes the methods, frequency, and responsibilities for the communication and reporting of the testing progress, status, issues, and results. The stakeholders identify the roles and responsibilities of the people involved in or affected by the testing activities, such as the test manager, the test team, the project manager, the developers, the customers, the users, etc. References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB Glossary of Testing Terms v4.0, Test Plan, Test Scope2
NEW QUESTION # 27
The following chart represents metrics related to testing of a project that was competed. Indicate what is represented by tie lines A, B and the axes X.Y
- A.

- B.

- C.

- D.

Answer: A
Explanation:
Option D correctly explains what is represented by the lines A, B and the axes X, Y in a testing metrics chart. According to option D:
X-axis represents Time
Y-axis represents Count
Line A represents Number of open bugs
Line B represents Total number of executed tests
This information is essential in understanding and analyzing the testing metrics of a completed project.
NEW QUESTION # 28
Which of the following statements about the value of maintaining traceability between the test basis and test work products is not true?
- A. Traceability can be useful for determining how many test basis items are covered by the corresponding tests
- B. Traceability can be useful for assessing the impact of a change to a test basis item on the corresponding tests
- C. Traceability can be useful for determining the most suitable test techniques to be used in a testing project
- D. Traceability can be useful to support the needs required by the auditing of testing
Answer: C
Explanation:
Explanation
Traceability is the ability to trace the relationships between the items of the test basis, such as the requirements, the design, the risks, etc., and the test artifacts, such as the test cases, the test results, the defects, etc. Traceability can provide various benefits for the testing process, such as improving the test coverage, the test quality, the test efficiency, and the test communication. However, not all the statements given are true about the value of maintaining traceability between the test basis and test work products. The statement that is not true is option C, which says that test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly. This statement is false, because test objectives are the goals or the purposes of testing, which can vary depending on the test level, the test type, the test technique, the test environment, the test stakeholder, etc. Test objectives can be defined in terms of the test basis, the test coverage, the test quality, the test risk, the test cost, the test time, etc. Test objectives should be specific, measurable, achievable, relevant, and time-bound, and they should be aligned with the project objectives and the quality characteristics. Test objectives should not be the same for all test levels, as different test levels have different focuses, scopes, and perspectives of testing, such as component testing, integration testing, system testing, and acceptance testing. The other statements are true about the value of maintaining traceability between the test basis and test work products, such as:
Traceability can be useful for assessing the impact of a change to a test basis item on the corresponding tests: This statement is true, because traceability can help to identify which tests are affected by a change in the test basis, such as a new requirement, a modified design, a revised risk, etc., and to determine thenecessary actions to update, re-execute, or re-evaluate the tests. Traceability can also help to estimate the effort, the cost, and the time needed to implement the change and to verify its impact on the software system.
Traceability can be useful for determining how many test basis items are covered by the corresponding tests: This statement is true, because traceability can help to measure the test coverage, which is the degree to which the test basis is exercised by the test cases. Traceability can help to identify which test basis items are covered, partially covered, or not covered by the tests, and to evaluate the adequacy, the completeness, and the effectiveness of the testing process. Traceability can also help to identify the gaps, the overlaps, or the redundancies in the test coverage, and to prioritize, optimize, or improve the test cases.
Traceability can be useful to support the needs required by the auditing of testing: This statement is true, because traceability can help to provide evidence, documentation, and justification for the testing activities, results, and outcomes. Traceability can help to demonstrate that the testing process follows the standards, the regulations, the policies, and the best practices that are applicable to the software system, the project, or the organization. Traceability can also help to verify that the testing process meets the expectations, the needs, and the satisfaction of the users and the stakeholders. References: ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 1.2.2, Testing Policies, Strategies, and Test Approaches1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.1, Test Planning1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.2, Test Monitoring and Control1 ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 2.1.3, Test Analysis and Design1 ISTQB Glossary of Testing Terms v4.0, Traceability, Test Basis, Test Artifact, Test Objective, Test Level, Test Coverage, Test Quality, Test Risk, Test Cost, Test Time2
NEW QUESTION # 29
Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?
- A. Test-Driven Development (TDD)
- B. Domain-Driven Design (DDD)
- C. Acceptance Test-Driven Development (ATDD)
- D. Behavior-Driven Development (BDD)
Answer: D
Explanation:
This answer is correct because Behavior-Driven Development (BDD) is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development. BDD is a collaborative approach that involves testers, developers, business analysts, product owners, and other stakeholders in defining the expected behavior of the application using scenarios that describe the preconditions, actions, and outcomes of the application. BDD scenarios are written using a domain-specific language (DSL) that can be translated into executable test cases using tools such as Cucumber or SpecFlow. BDD aims to improve communication, collaboration, and feedback among the team members, and to deliver software that meets the customer's needs and expectations. Reference: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 3.1.1.4
NEW QUESTION # 30
Which of the following is a task the Author is responsible for, as part of a typical formal review?
- A. Identifying potential anomalies in the work product under review
- B. Fixing the anomalies found in the work product under review
- C. Determining the people who will be involved in the review
- D. Recording the anomalies found during the review meeting
Answer: A
Explanation:
Explanation
This answer is correct because identifying potential anomalies in the work product under review is one of the tasks the Author is responsible for, as part of a typical formal review. The Author is the person who creates the work product to be reviewed, such as a requirement specification, a design document, or a test case. The Author's tasks include preparing the work product for the review, identifying potential anomalies in the work product, and fixing the anomalies found in the work product after the review. References: ISTQB Glossary of Testing Terms v4.0, ISTQB Foundation Level Syllabus v4.0, Section 2.4.2.1
NEW QUESTION # 31
The tests at the bottom layer of the test pyramid:
- A. are defined as 'Ul Tests' or 'End-To-End tests' in the different models of the pyramid
- B. cover larger pieces of functionalities than the tests at the top layer of the pyramid
- C. run faster than the tests at the top layer of the pyramid
- D. are unscripted tests produced by experience-based test techniques
Answer: C
Explanation:
Explanation
The tests at the bottom layer of the test pyramid run faster than the tests at the top layer of the pyramid because they are more focused, isolated, and atomic. They usually test individual units or components of the software system, such as classes, methods, or functions. They are also easier to maintain and execute, as they have fewer dependencies and interactions with other parts of the system. The tests at the top layer of the test pyramid, on the other hand, are slower because they cover larger pieces of functionalities, such as user interfaces, workflows, or end-to-end scenarios. They also have more dependencies and interactions with other systems, such as databases, networks, or external services. They are more complex and costly to maintain and execute, as they require more setup and teardown procedures, test data, and test environments. References:
ISTQB Certified Tester Foundation Level (CTFL) v4.0 sources and documents:
ISTQB Certified Tester Foundation Level Syllabus v4.0, Chapter 3.2.1, Test Pyramid1 ISTQB Glossary of Testing Terms v4.0, Test Pyramid2
NEW QUESTION # 32
Which of the following applications will be the MOST suitable for testing by Use Cases
- A. Suitability and performance of a Multi media (audio video based) system to a new operating system
- B. A billing system used to calculate monthly charge based or large number of subscribers parameters
- C. Accuracy and usability of a new Navigation system compared with previous system
- D. The ability of an Anti virus package to detect and quarantine a new threat
Answer: C
NEW QUESTION # 33
......